During the month of August, 50 work orders were submitted to the facilities department, and 63 work orders were completed district-wide.
The maintenance department repaired exterior lights throughout the district and installed electrical lined to accommodate new Smart Boards in all schools.
- Repair of corridor wall tiles is in progress in several locations throughout the building.
- Maintainers rebuilt and repaired several sections of outdoor sprinkler systems.
- Reconstruction of outside overhangs has continued in several locations.
- Electrical and plumbing repairs were completed in classrooms and corridors.
- Carpenters and masons completed repairs in various locations throughout the building.
- Plumbing and electrical repairs were completed throughout the building.
- Carpenters constructed shelf storage and repaired doors in several locations.
- Painting of trim (door frames, windows and shelves) has continued.
- Painting of the kitchen and nurse's office is complete.
- Painting of the walls and trim in the gymnasium and ceiling, walls and trim in the all purpose room is complete.
- Carpentry, plumbing and electrical repairs were completed in several locations.
- Plumbing and electrical repairs were completed throughout the building.
- Electrical repairs were completed in several locations.
- Repairs to several sections of the outdoor sprinkler system continued.
- Masonry repairs are in progress under the 2010-11 capital improvement program.
- District masons completed several repairs to the exterior of the building.
- Plumbers completed repairs to the outdoor sprinkler system.
- Plumbing and electrical repairs were completed in several locations.
- Electrical lines were run in classrooms to accommodate IEP requirements.
- Electrical and masonry repairs were completed for the sports tower.
- Contractors replaced a large area of the parking lot under the 2010-11 capital improvement program.
/
- Electricians ran new electrical lines to accommodate IEP requirements.
- Maintainers installed cabinets and appliances in the new special education life skills classroom.
- Plumbing, carpentry and electrical repairs were completed in several locations, including major plumbing repairs in the girls locker room.
- Electrical, carpentry and plumbing repairs were completed throughout the building.